Pages
- About the Content
- About Us
- Costa Rica Property Law - Squatter’s vs. Landowner’s Rights
- RSS Costa Rica Real Estate
Categories
Archives
- December 2008
- November 2008
- October 2008
- September 2008
- August 2008
- July 2008
- June 2008
- May 2008
- April 2008
- March 2008
- February 2008
- January 2008
- December 2007
- November 2007
- October 2007
- September 2007
- August 2007
- July 2007
- June 2007
- May 2007
- April 2007
- March 2007
- February 2007
- January 2007
- December 2006
- November 2006
- October 2006
- September 2006
- August 2006
- July 2006
- June 2006
- May 2006
- April 2006
- March 2006
- February 2006
- January 2006
- December 2005
- November 2005
- October 2005
- September 2005
- August 2005
Meta
Autor: rod
~ 21/05/07
by Rod Hughes
The Moin III thermal plant in Limon province suffered no fewer than 95 breakdowns since its installation in May 2003 but finally last April 3 a piece of metal broke loose and was sucked into a turbine, severely damaging its blades and resulting in a serious shortage of electricity and a two-week period of power rationing, according to an exclusive story in the daily La Nacion Monday.
The Moin plant, purchased from the Japanese company Marubeni at a cost of $50 million, failed no fewer than 95 times in the four years of its life, according to an investigative report by La Nacion’s Mercedes Aguero and Esteban Oviedo. The National Power and Light Co. purchased the 40 megawatt thermal plant (powered by fossil fuel) but it was subsequently leased by the Costa Rican Electrical Institute (ICE) and, despite its dismal service record, inexplicably bought by ICE last year.
According to the newspaper, the Moin III plant also suffered from fuel purification troubles and contamination of the generator from leaking oil. Due to the constant breakdowns and long downtimes, the plant was only on line 30% of the time between 2003 and 2005, the reporters found. Moreover, delays in repair ICE blames on the company caused ICE to complain to Marubeni about a lack of “diligence” in their service.
In another controversial twist, the Power and Light Company returned to Marubeni a $5 million bond guarantee of proper plant functioning in September of 2004. ICE’s official defense is that defects in the plant did not begin showing up until after that expiration date. But journalist Mercedes Aguero quotes ICE assistant manager Manuel Obregon as saying that the defects in the machinery showed up all through 2003.
But this is not the end of ICE’s woes. The older plant Moin II also went down in April and will cost $4.5 million to repair. This thermal plant went on line in 1995 and ICE said it was time for an overhaul. It is scheduled to go back in service by next dry season.
No Comments »
No comments yet.
RSS feed for comments on this post. TrackBack URL
Leave a comment
You must be logged in to post a comment.