Pages
Categories
Archives
- October 2008
- September 2008
- August 2008
- July 2008
- June 2008
- May 2008
- April 2008
- March 2008
- February 2008
- January 2008
- December 2007
- November 2007
- October 2007
- September 2007
- August 2007
- July 2007
- June 2007
- May 2007
- April 2007
- March 2007
- February 2007
- January 2007
- December 2006
- November 2006
- October 2006
- September 2006
- August 2006
- July 2006
- June 2006
- May 2006
- April 2006
- March 2006
- February 2006
- January 2006
- December 2005
- November 2005
- October 2005
- September 2005
- August 2005
Meta
Autor: rod
~ 30/04/07
When Costa Rica’s newest hospital opened its doors in San Rafael de Alajuela 18 months ago, area residents—some half a million to be served by the facility—were euphoric. Today, the hospital is barely running, reports the daily newspaper La Nacion.
Of the 700 new posts for medical personnel, only 153 have been filled by the Social Security administration (Caja), the giant government agency that runs public hospitals. Those 153 are running at full speed to tend the patients.
Three ultramodern operating rooms cannot be used simultaneously because of the personnel scarcity—especially anathesiologists. Some 400 patients are home awaiting urinology operations and 300 women need gynolocogy surgery. The whole list numbers a staggering 7,000 pending operations and the wait for 1,600 of those is up to 30 months.
Meanwhile, a large portion of recent medical school graduates languish without work.
Of 310 beds, only 226 are in use and that is only seven more than the old, ramshackle hospital the new facility replaced in October, 2004, reports La Nacion. The rest have not even shed their protective plastic covers from the factory and nurses’ desks on the third floor sit gathering dust.
Consulted by the newspaper, a spokesperson for the Caja assure that a “new strategy” to cure the problem was being developed but hospital director Luis Diego Alfaro countered that the strategy included only longer hours for the already overworked staff.
The hospital has been star-crossed from the beginning, according to the report. In August, 2000, seven construction firms competed for the construction contract with a Spanish company getting the nod in December of that year, but it was not until May, 2001, that the $34 million contract was signed after legal appearls by the other companies. But by September of that year, it was found that the ground under the site was a boggy clay that needed another $2 million preparation to assure safe construction. In 2005, the Caja discovered serious flaws in the work—doors badly designed, medical equipment that did not work and some electrical connections unuseable—but too late to get them repaired under the warrantee.
No Comments »
No comments yet.
RSS feed for comments on this post. TrackBack URL
Leave a comment
You must be logged in to post a comment.